Morningside Park's Baywalk Is Running Late. Its Kayak Launch Has a Longer Wait.

Behind the construction fence along Morningside Park's shoreline, the City of Miami is building a 2,250-foot baywalk along 1,200 feet of new seawall. It will come with trails, new trees, solar lighting, benches, a water fountain and an upgraded boat ramp with better parking. One thing that used to make this shoreline worth a Saturday morning is not on that list. A kayak or paddleboard you could rent at the water's edge depends on a separate City decision, and no date has been announced for it. The seawall is late. The paddling has a longer wait.

A Summer Deadline That Came and Went

The City's Morningside Park Waterfront Improvements page still carries the original schedule. Phase I would start in December 2024, and it "should be completed in Summer 2026." The fence went up on schedule. The shoreline closed to cars and pedestrians by December 2, 2024, and construction began December 4.

The page's photo updates show the work moving along. Sheet pile installation was finished by spring 2025, and drone photos followed in August 2025, November 2025 and January 2026. The most recent update is labeled "Work in Progress - August 2026." It shows the south and north sides of the project still under construction, in the last month of the summer the City had targeted. As of that August update, the City had not posted a new completion date or a reopening announcement.

The City lists the project cost at $16,886,344 and presents it under its Miami Forever Bond program. By the City's own measure, the bayfront edge of the park has now been closed for nearly two years. For anyone who walks the park daily, the real question is what comes back when it reopens, and in what order.

What Reopens, and What Each Piece Is Waiting On

The pieces of Morningside's waterfront are on different clocks. Some are part of the construction contract. Others need a separate City process, or are on hold for reasons that have nothing to do with the seawall.

Piece of the waterfront Where it stands What it depends on
Seawall, baywalk, trails, lighting Under construction as of August 2026 Finishing Phase I
Boat ramp, floating dock, parking Part of Phase I upgrades Finishing Phase I
Kayak and paddleboard rentals No full-service concession since November 2024 A new City concession bid with no announced date
Swimming pool Listed by the Morningside Civic Association as "CLOSED indefinitely" Not part of this project
West side drainage and landscaping Defined as Phase II No start or finish date posted

The two rows from the top of the table will come back together, because they share one contract. The kayak row is different, and it has the longest wait.

Why the Kayaks Left Before the Fence Went Up

The paddling business left Morningside a month before construction started. WLRN reported in November 2024 that the City had ordered Morningside Watersports to stop operating. According to the City, the operators did not have a City of Miami Certificate of Use or a Business Tax Receipt, and their sublease to So Flo Water Adventures had not been authorized. A November 1 letter told the owners to close by November 8. WLRN also noted that a PADL self-service paddleboard kiosk had been at the park at the time.

The City has said a concession will return. Its project description talks about improving the area "for Kayak concession operations" and lists a kayak launch alongside the boat ramp. According to WLRN's report, the Parks Director said the City expected to open bidding for a new watersports operator once the improvements were finished, but that "no specific date for the bid has been set." The order matters here. The bid follows the construction, and an operator follows the bid. The launch can be finished before anyone is renting boats from it.

One more detail for neighbors who check the civic association's site. The Morningside Civic Association's park page still lists Morningside Water Sports as open daily from 10 a.m. to 6 p.m. That listing is out of date, since WLRN reported the City's shutdown order in November 2024.

The 15 Feet Everyone Argued About

The baywalk taking shape behind the fence is the same one that drew protesters to the groundbreaking. WLRN described city leaders trying to talk over loud jeers on December 4, 2024, at a project the station called more than a decade in the making. According to WLRN, the protesters generally supported renovating the park. Their objection was the baywalk's 15-foot width, which they said would take away green space and plant life. They asked the Commission to change zoning rules so a narrower path would be allowed. One sign read "15 feet kills the median and trees." The City said the surface would be semi-permeable.

The neighborhood was divided too. The Biscayne Times reported that members of the Morningside Civic Association board disagreed. Some supported moving ahead, and another opposed the hard-surface design. The path went ahead at the planned width. When the fence comes down, neighbors will finally be able to judge a debate they have only seen as renderings and drone photos. The design gives a walker a continuous bayfront route of more than four-tenths of a mile, lit by solar fixtures, where the shoreline used to be patchy.

The Side of the Park That Never Closed

While the shoreline was fenced off, the City kept the western side of the park open. That part of the park still does most of the daily work. According to the City's Morningside Park directory listing, the park is open 7 a.m. to 9 p.m. The civic association's page lists shorter hours, closing at 7 p.m., so check before planning an evening visit.

Here is what the City lists on the open side:

  • Tennis center: weekdays 7 a.m. to 9 p.m., weekends and holidays 7 a.m. to 6 p.m.
  • Recreation center, playground and outdoor gym equipment
  • Dogs on leash: the City listing does not describe a fenced dog run

Pickleball players will need to go elsewhere. Morningside is not on the City's list of designated pickleball sites. The directory gives the boat ramp's hours as 8 a.m. to 6 p.m. daily, but the ramp sits inside a fenced construction zone. Call the park office before trailering a boat over.

Building a Saturday Around the Wait

With the bay side still closed, a morning at Morningside works best as one stop on a longer loop up Biscayne Boulevard. Legion Park is about a dozen blocks north at 6601 Biscayne Blvd. It hosts the Urban Oasis Project's Legion Park Farmers Market on Saturdays from 9 a.m. to 2 p.m., with free parking in the main lot at 6447 NE 7th Ave. The organizer describes its markets as running year-round except in extreme weather.

The rest of the MiMo corridor gives you a lunch stop. The Infatuation's new-openings guide lists La Fraiche Pasta Box, at 5700 Biscayne Blvd., Suite 109, as a fast-casual pasta counter where you choose the shape, sauce and toppings. It also sells dry pasta by the pound. Farther up the boulevard, at 7285 Biscayne Blvd., the Caracas Bakery team has put "fall 2026" and "neighborhood rotisserie" in the window of Teo Teo, a planned Venezuelan rotisserie that The Infatuation listed as an upcoming opening in late September.

For the afternoon, Upper Eastside Hangout opened in August at 701 NE 79th St. in Little River. Miami New Times reported that it took over the former Anderson property and a liquor license dating to 1937. The open-air space holds more than 250 people, with a 15-seat cocktail shack, lawn games, big screens and food from Cheeseburger Baby, Tacomiendo and Noodle Bar.

What to Watch For

When the City updates its project page again, the baywalk and boat ramp will be the first news. The next thing to watch is a concession solicitation for the kayak launch, because that, not the ribbon-cutting, is what brings rentals back to Morningside's shoreline. Phase II will follow on the western side, with drainage improvements and landscaping. As of the City's latest posting, it has no dates. Questions about the park can go to the park office at 305-795-1834, the number on the civic association's park page.

A park project with this many moving parts affects what nearby waterfront homes feel like to live in, room by room and season by season. If you live near Morningside and want to understand how the reopened shoreline might change your home's daily appeal, Shayna Hanson is happy to walk through it with you. Request a Private Consultation, and we'll discuss what the new bayfront means for your property on your schedule.

Work With Shayna

Working for Fortune 100, 200 and 500 clientele in Business Development and Public Relations in both the United States and Latin America has given Ms. Davidov Hanson an acute sense of business savvy, negotiation skills and the ability to relate and work with an array of personalities, cultures and levels of sophistication.